House construction cost calculator
A 2,000 sq ft house built at 150 per sq ft, with 10% for design and permits and a 10% contingency, comes to about 363,000. Type your own area and rate to see yours.
- Free
- No sign-up
- Runs in your browser
363,000for 2,000 sq ft at 150 per sq ft, with fees and contingency
- 181.5 per sq ft all in
- 1,953.65 per sq m
- 185.81 sq m built
- Building cost before fees
- 300,000
- Design, permits and fees
- 30,000
- Buffer added
- 33,000
- Land
- 0
- Whole project with land
- 363,000
| Step | Amount |
|---|---|
| Area x rate (2,000 x 150) | 300,000 |
| Design, permits and fees (10%) | 30,000 |
| Cost before contingency | 330,000 |
| Contingency (10%) | 33,000 |
| Construction estimate | 363,000 |
| Land | 0 |
| Whole project | 363,000 |
How to use the House Construction Cost Calculator
- Choose Square feet or Square meters under Area unit, then type the Built area with every floor added.
- Enter the Building cost per unit of area from a local builder quote or your own estimate.
- Set Design, permits and fees and Contingency as percents, and add the Land cost if you want the whole project.
- Read the estimate, the cost per unit in both systems and the step table, and change one box at a time to compare.
How do I calculate house construction cost?
The sum has three steps. First multiply the built area by the cost per unit of area. For 2,000 sq ft at 150 that is 300,000. Second, add design, permits and fees as a percent of that figure: 10% is 30,000, which brings the running total to 330,000. Third, add a contingency as a percent of the running total: 10% is 33,000. The last figure is the building estimate, 363,000.
Divided by the area, that is 181.5 per sq ft all in, which is 1,953.65 per square meter on a house of 185.81 square meters. The all in figure is the one to compare with other quotes, because a bare rate per unit leaves out fees and the buffer.
Built area means the floor area of every storey that gets built, walls included. A plot of 5,000 sq ft with a two storey house of 1,000 sq ft on each floor has a built area of 2,000 sq ft, not 5,000.
What cost per square foot or meter should I use?
Nobody can give a single worldwide number, because labor, materials, soil, the number of bathrooms, the roof and the level of finish all move the price. The calculator therefore stores no price list. You type the rate, and a written quote from a local builder or contractor for a similar house is the best source. If you have only a rough figure, run three rates and read the spread, as in the table.
Each step of 15 in the rate moves the total by 36,300 on this house, since the fees and the contingency scale with it.
| Rate per sq ft | Area x rate | Estimate | All in per sq ft |
|---|---|---|---|
| 120 | 240,000 | 290,400 | 145.2 |
| 135 | 270,000 | 326,700 | 163.35 |
| 150 | 300,000 | 363,000 | 181.5 |
| 165 | 330,000 | 399,300 | 199.65 |
| 180 | 360,000 | 435,600 | 217.8 |
How much contingency should a building budget carry?
A contingency pays for what the drawings do not show: a price rise in steel or lumber, rock found while digging, or a change of tiles halfway through. The right percent depends on how finished the design is and how stable prices are, so ask your builder and your lender what they use. This tool takes the percent you type and applies it to the cost including fees. The table keeps everything else fixed and moves only that percent.
At 0% the estimate is 330,000. Every 5 points of contingency add 16,500 here, because 5% of 330,000 is 16,500.
| Contingency | Buffer amount | Estimate |
|---|---|---|
| 0% | 0 | 330,000 |
| 5% | 16,500 | 346,500 |
| 10% | 33,000 | 363,000 |
| 15% | 49,500 | 379,500 |
| 20% | 66,000 | 396,000 |
How does the size of the house change the total?
With the same rate and percents the total grows in a straight line with area, so doubling the area doubles the estimate. The row for 3,000 sq ft costs 544,500, three times the 1,000 sq ft row at 181,500. Real projects are less tidy: a small house has a higher cost per unit because a kitchen and two bathrooms cost much the same in a big house or a small one. Replace the rate when you change the size a lot.
Working in metric works the same way. A house of 200 square meters at 1,600 per square meter, with 8% fees and a 5% contingency, comes to 362,880, which is 1,814.4 per square meter, or 168.56 per sq ft on 2,152.78 sq ft.
| Built area in sq ft | Area x rate | Estimate | All in per sq m |
|---|---|---|---|
| 1,000 | 150,000 | 181,500 | 1,953.65 |
| 1,500 | 225,000 | 272,250 | 1,953.65 |
| 2,000 | 300,000 | 363,000 | 1,953.65 |
| 2,500 | 375,000 | 453,750 | 1,953.65 |
| 3,000 | 450,000 | 544,500 | 1,953.65 |
The optional Land cost is added after the contingency, so it is not marked up by fees or buffers. With 120,000 of land the whole project here is 483,000. Utility connections, landscaping, furniture and finance costs are separate lines, so add them to the land box or keep a note of them if the builder's quote leaves them out. For a loan on the project, see the mortgage calculator, and for materials such as concrete or paint, use the tools made for those.
Use it with
- Concrete Calculator: bags or cubic yards for slabs and posts.
- Mortgage Calculator: payment with tax and insurance.
- Roofing Calculator: roof area and squares.
Questions
How much does it cost to build a house?
It depends on the rate where you build. Area times rate gives the base: 2,000 sq ft at 150 per sq ft is 300,000 before fees and contingency. Replace the example rate with a quote.
How do I calculate construction cost per square foot?
Divide the total building cost by the built area. The estimate of 363,000 over 2,000 sq ft is 181.5 per sq ft. The calculator shows this and the per square meter figure.
Is land included in the construction cost?
Not unless you type it into the Land cost box. The building estimate stays at 363,000 and the whole project line adds the land, 483,000 with 120,000 of land.
How do I convert square feet to square meters for a build?
Multiply square feet by 0.09290304. 2,000 sq ft is 185.81 square meters. Going the other way, divide square meters by 0.09290304.
What is a contingency in a construction budget?
A buffer, shown as a percent of the cost so far, for items the plan does not price. At 10% it adds 33,000 to this example, and the rows above show other percents.
Is this a quote for my house?
No. It is a planning estimate from the rate and percents you enter. A quote from a licensed builder, based on drawings, is the figure to rely on.
The tool's results are computed in your browser by the code on this page; the explanations are checked against the tool's own output.